• 2021 December 5 11:51

    Vuosaari fairway deepening project completed on schedule, safely and under budget

    The deepening of the Vuosaari fairway and harbour basin was completed ahead of schedule at the end of November. During the project, around 1.1 million cubic metres of soil was dredged and 800,000 cubic metres of rock was made available for use in area construction in Helsinki.

    The project was completed on schedule and under budget. The project, which started in spring 2020, cost 26.5 million euros. The original budget estimate was over 10 million euros more. The project has also been awarded a 20% EU CEF grant to improve transport efficiency and reduce environmental hazards. The project was under budget thanks to a favourable market situation, good advance planning and the competence of the contractor.

    “The biggest single factor contributing to staying under budget was that the Vuosaari contract was tendered at the same time as the City of Helsinki’s Hernesaari dredging and filling contract, which made it possible to get a good bid for both. The chosen contractor, Terramare Oy, also has high-quality equipment and experienced personnel, which make for efficient work,” says Seppo Paukkeri, Project Manager at the Finnish Transport Infrastructure Agency.

    “In addition to the concurrence of the two projects, the contractor’s previous experience in the construction of the Vuosaari fairway contributed to staying under budget,” says Jukka Kallio, VP Cargo at the Port of Helsinki.

    For Terramare, the project was a typical dredging project in terms of difficulty. According to Vyyryläinen, the special characteristics of the project included the busy vessel traffic and the water intake of the power plant in the work area.

    “The project was successfully completed with good advance planning, the project’s own innovations and the help of motivated and skilled personnel,” says Jani Vyyryläinen from the contractor, Terramare.

    The construction consultant and supervisor for the project was Ramboll CM Oy. Ramboll also acted as project planner, geotechnical expert, safety coordinator, risk management expert and environmental expert and was responsible for the project’s communications during construction.

    The project to deepen the Vuosaari harbour basin and fairway was completed on schedule, with 70 per cent of the budget spent.
    Deepening work carried out safely amidst busy ship traffic
    Safety was the top priority of the project, and the project team is pleased that the work was carried out safely all the way to the end. The project was carried out on a busy water area and required significant efforts to coordinate the vessel traffic, pleasure boating and work machinery. Vuosaari Harbour was kept open throughout the deepening project.

    “The Vuosaari fairway has the busiest vessel traffic in Finland. The dredging and excavation work had to be carried out in the fairway in such a way that large cargo ships could safely pass. Every week, we had a joint traffic meeting in which we went through the upcoming work with the pilots of the VTS vessel traffic service, the shipping companies and the contractor and agreed on the rules to ensure safety. Although the work required additional signage and speed restrictions, all parties involved in the project were willing to be flexible and contribute to the safe implementation of the project,” says Paukkeri appreciatively.

    “Throughout the project, reconciling the work and the safety of vessel traffic was a major challenge that was constantly invested in by the different parties involved. However, close cooperation between the project’s traffic coordinator and other parties involved created good practices for the safe implementation of the project,” says Vyyryläinen.

    Larger ships will have access to Vuosaari in the future
    Vuosaari Harbour is Finland’s busiest container harbour. The fairway is used by approximately three thousand vessels per year. Thanks to the deepening, Vuosaari Harbour will be able to receive larger container ships in the future. This will reduce the environmental impact of container transport, as larger loads can be transported at a time. At the same time, the use of larger ships will reduce transport costs.
    “Vuosaari is Finland’s most important main port for international trade. The project is important for the Port, but even more important for the Port’s customers and, by extension, for Finland’s international trade,” says Jukka Kallio of the Port of Helsinki.

    The new fairway was officially opened on 30 November 2021.

    Building new Helsinki with excavated rock
    Most of the rock excavated during the project, 800,000 cubic metres, was transported by water 21 km away to Hernesaari, where it was used for sea filling in the area. The amount of rock transported could fill the Finnish Parliament House approximately seven times. Transporting the materials exceptionally by sea reduced the environmental impact, traffic congestion and costs of transport.

    “The transport by sea significantly reduced lorry traffic on the streets of Helsinki. The solution replaced about 40,000 lorry loads and reduced fuel consumption by 1.1 million litres and carbon emissions by about 2,500 tonnes,” says Mikko Suominen, Land Mass Coordinator of the City of Helsinki.

    In the 2020s, Hernesaari will be transformed through construction into a maritime residential area focused on tourism and leisure services, with port and industrial functions moving elsewhere.

    Project followed by additional work to widen the buoy gate
    In front of Vuosaari Harbour, there is still a point that is narrow for ships, the so-called buoy gate. The project will now be followed by the widening of the buoy gate. The work has been granted a water permit by the Regional State Administrative Agency. The widening of the buoy gate is well suited to be carried out in the wake of a larger project, reducing the overall negative impact. Autumn is a good time to carry out the widening work from the cabin owners’ point of view as well. The work started in October and will be completed at the turn of November and December (the project will end for contractor Terramare).

    In addition to the widening of the buoy gate, further work will be carried out in 2022 on the deepening of the Kuiva Hevonen marina and the construction of a breakwater. Both of these additional works are part of the EU funding.

    New ways of working reduced environmental impact
    The rock masses excavated during the work were utilised in area construction in Helsinki, and their transport to the construction site by sea reduced the environmental impact, traffic congestion and costs caused by the transport.
    The environmental impact of the work was monitored regularly. The impact of the project on the fish stock will continue to be compensated for by stocking 40,000 young whitefish in the area every year until 2023. This year’s whitefish stocking took place at the end of September.

    The impact of the project on the waters was closely monitored throughout the project through turbidity measurements and surveys, aerial and satellite images and water sampling. Based on these, the impacts have been found to be as predicted. The turbidity was limited to the area around the work machinery, and particularly during the spring runoff period, it was difficult to distinguish the turbidity from the load of solid matter carried by the rivers and the resulting general turbidity.

    The environmental monitoring of the project included investigating the presence of various harmful substances in the marine area. The harmful tributyltin used in the anti-fouling paint of boats was the subject of a heated debate during the construction of Vuosaari Harbour in the early 2000s. However, the tin compound in question was no longer present during the current deepening work. The dredging extended to the deeper level of the now existing fairway.

    During the project, underwater noise from the dredging and excavation work was also investigated. The report provided important information on the construction impacts of waterway projects for the protection of the Baltic Sea. You can read the article and report on underwater noise here. The report on the 2021 monitoring results will be published on the project website after the report is completed in the summer of 2022.




18 мая 2024

14:28 Танкер загорелся у берегов Йемена после попадания ракеты
12:09 Судно получило повреждения в районе Йемена
09:01 Введен временный запрет на вывоз отходов и лома драгоценных металлов из России
08:38 Противолодочный корабль «Уренгой» провел тренировки по отражению атак в Калининградской области
08:08 Глава правительства РФ Михаил Мишустин утвердил распределение обязанностей между заместителями
08:06 Десантный корабль «Мордовия» выполнил учебные стрельбы
08:00 АСОП поздравляет с юбилеем Артура Седова!
07:45 ИАА «ПортНьюс» поздравляет с юбилеем управляющего директора АО «Ростерминалуголь» Артура Седова!

17 мая 2024

19:00 На Панамском канале в апреле 2024 года отмечено снижение потребления бункерного топлива
18:41 Морспасслужба рассчитывает получить 16 судов для работы на СМП в 2025 году
18:23 Туапсинский балкерный терминал в апреле 2024 года увеличил погрузку минудобрений на суда на 50%
18:08 Марат Хуснуллин: Планируется максимальное развитие водных путей для обеспечения связи между портами Каспия
17:54 ЛСП «Северный полюс» прибыла в порт Мурманска после первого высокоширотного рейса
17:45 Итоги недели с ПортНьюс 13-17 мая
17:22 Минсельхоз: К 2030 году планируется построить 20 сухогрузов для сельхозпродукции
16:51 Судно «Валдай 45Р-18» выполнило тестовый рейс по маршруту Ростов-на-Дону — Семикаракорск
16:34 Грузоперевозки в Беломорско-Онежском бассейне с начала навигации 2024 года к середине мая снизились на 16,4%
16:17 Газпром надеется получить от СНСЗ законченный проект спасательной шлюпки через несколько лет
15:58 Великобритания ввела санкции в отношении «Восточной стивидорной компании»
15:23 РС оказал содействие Юридическому комитету ИМО в рассмотрении вопросов фиктивной регистрации судов
14:51 Эксперт: Коммерческому внедрению автономных судов мешают ИМО, профсоюзы и «узкие места» в технологиях
14:32 Специалисты считают перспективным использование экранопланов в арктических перевозках
14:15 Водный транспорт ООО «Транснефть – Балтика» подготовлен к навигации
13:54 Кассация подтвердила запрет Wartsila вести судебные споры с Балтзаводом вне России
13:37 Бункеровочное судно врезалось в опору моста в Техасе
13:18 Продажи судового топлива в порту Фуджайра (ОАЭ) в апреле 2024 года составили почти 639 тыс. куб. м
12:56 Флот Севмаша (Архангельская область) открыл навигацию 2024 года
12:42 Глава Росатома: Принято решение о создании подкомиссии России и Китая по Севморпути
12:31 Паром «Сахалин-9» с 20 мая будет выведен с линии Ванино — Холмск на плановое техобслуживание
11:59 Вторая партия экспортного груза отправится из ММРП по мультимодальному маршруту
11:29 Владимир Путин: Россия готова предоставить инвесторам из КНР экономические льготы
11:10 ГТЛК проавансировала строительство 12 барж и 3 буксиров на Череповецком судостроительном заводе
10:48 На Городецком гидроузле проведено регулярное обследование шлюзов, плотин и дамб
10:33 Росморпорт планирует доковый ремонт дизель-электрического ледокола «Капитан Чудинов»
10:07 Теплоход «Адмирал Невельской» вернулся на линию Корсаков ‒ Курилы после ремонта
09:46 Суда FESCO в мае 2024 года совершат 5 рейсов во Вьетнам
09:24 «K» Line опробовала биотопливо марки B100 при рейсе морского автовоза Apollon Highway
09:02 ФГБУ «ГлавСевморпуть» призывает к совместному изучению ледового сжатия при судоходстве по СМП
08:39 В Астраханском вузе Росрыболовства провели испытания нового подводного робота
08:21 ААНИИ завершил первый этап модернизации автоматизированной ледово-информационной системы «Север»
08:00 Эксперт: помимо дисбаланса в развитии портов и железных дорог существуют проблемы с технологиями их взаимодействия

16 мая 2024

19:00 РС объявил конкурс 2024 года на лучшую выпускную квалификационную работу
18:48 ААНИИ в 2024 году планирует открыть 58 станций мониторинга вечной мерзлоты
18:37 XV Международный салон «Комплексная безопасность» пройдет с 29 мая по 1 июня 2024 года
18:24 ААНИИ: Принципиально тяжелых ледовых условий для летней навигации 2024 года на СМП не ожидается
18:11 Универсальный паром «Антей» отправился в первый рейс на линии Усть-Луга — Балтийск
17:56 Технический проект НЭС «Иван Фролов» завершен
17:43 Губернатор: Грузооборот порта Мурманск к 2027 году увеличится на 63 млн тонн
17:24 Выручка немецкой группы HHLA за январь-март 2024 года сократилась на 0,3% — до 363,6 млн евро
17:02 НИС «Академик Опарин» планируется отремонтировать до 20 декабря 2024 года
16:39 Российские ученые в 2025 году начнут поиск древнего льда возрастом 1,5 млн лет в Антарктиде
16:17 Новый земснаряд проекта 4395 «Евгений Плескевич» буксируется в Алтайский край
15:55 Навигация 2024 года открылась на Саяно-Шушенском водохранилище
15:33 В России создан технический комитет для разработки стандартов в сфере логистики и управления цепями поставок
15:16 Перевозка экспортных удобрений по сети РЖД в январе-апреле 2024 года выросла на 20,7% — до 10,7 млн тонн
14:54 Исследование: Более 95% наиболее распространенных скрубберов окупаются за 5 лет
14:29 Перевозки контейнеров на СКЖД в январе-апреле 2024 года снизились на 7,1%
14:11 Китайская компания может инвестировать в развитие терминала «Глобал Портс» в Усть-Луге
13:50 Суда в Красном море начали маскироваться под китайские через манипулирование сигналами АИС
13:32 Ливадийский РСЗ (Находка) заложил пассажирский катамаран проекта HSC200
13:13 Опыт Гуанчжоу поможет Хабаровскому краю в развитии транспортного узла Ванино и Советской Гавани
12:56 СРЗ «Красная Кузница» (Архангельск) спустил на воду сухогруз «Териберка» после докового ремонта
12:34 Росимущество передало региону 18 участков и 9 объектов в порту Магадан для создания рыбного порта
12:18 Мурманский морской торговый порт готовится ввести в эксплуатацию новый грейферный погрузчик
11:57 В Енисейском пароходстве прошло тестирование автономной спасательной шлюпки танкера «ТН-663»
11:39 Судостроительный проект «Норебо» в Ленобласти возглавил Алексей Тоболев
11:24 Для морских терминалов «Глобал Портс» на Северо-Западе закуплены два новых перегружателя-ричстакера
11:03 Морспасслужба получит 6 ТНПА в составе строящихся специализированных судов
10:42 Владимир Путин: Экспорт российского продовольствия на китайский рынок в 2023 году вырос в 1,5 раза
10:31 Началась установка модульного причала на речном вокзале Пермь-I